CONCRETE WORKS OF COLORADO
HOME ABOUT US PROJECTS AWARDS WHAT'S NEW SAFETY IN THE NEWS  
SPACER
 
       
Featured Projects

14th Street Sidewalk/Streetscape Project

   
       

Broadway Transportation Improvements Project (Boulder)

14th Street

Tennyson St.

S. Broadway
Reconstruction/ Wesley to Yale

Airport Projects
  - Grand Junction Regional
  - Riverton Regional
  - Gunnison-Crested Butte

30th Street Transportation Improvements Project

Conduit 74

S. Broadway
Reconstruction/ Arizona to Iowa

WYDOT - Gillette/Douglas
HWY 59

Ferril Lake at City Park

University Blvd./E. Asbury Ave. Reconstruction

Larimer Square

Hanging Lake Tunnel

Elmer's TwoMile Greenway Project

Denver Water Conduit
Project #25

Winslow Road

GCC Dacotah Cement Terminal

28th & Pearl Improvement Project

Broadway Street & Bridge Reconstruction

Foothills Parkway
& Arapahoe

Glenwood Canyon

Grand Avenue Paving

Roundabouts

Santa Fe Dr. & Belleview

Utilities

14th-final

Project Overview:
This $14,000,000 bond reconstruction project along one of the busiest corridors in downtown Denver, from Market to Colfax, was completed in November, 2011. Improvements included: widening the northern sidewalk to 19 feet and reconstructing the southern sidewalk to 16 feet. Bulb outs were added to the south side to minimize the pedestrian crossing distance across 14th Street.

Improvements along the sidewalk include:

  • granite seating areas,
  • elongated planters and planter pots with annual plantings,
  • shrubs,
  • trees,
  • street lighting, accent lighting, and wayfinding signage.

Several blocks were reconstructed in concrete. The project took approximately 13 months to complete.

Project history:
From 2005-2009 the Downtown Denver Partnership sponsored the 14th Street Initiative in cooperation with the City and County of Denver.  This 14th Street Initiative was aimed at creating a vibrant downtown corridor on 14th Street between Market and Colfax that builds upon the substansial private investment along the cooridor.  In 2007 with the successful passage of the Better Denver Bond Program, $10 million was earmarked for this project.


14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

14th Street - Concrete Works of Colorado

 

 

 

       

Community Involvement         Project Recognition         Employment         Contact Us

 

 

All Rights Reserved. Concrete Works of Colorado