CONCRETE WORKS OF COLORADO
HOME ABOUT US PROJECTS AWARDS WHAT'S NEW SAFETY IN THE NEWS  
SPACER
   
Featured Projects Denver Water Conduit Project #25
   

Broadway Transportation Improvements Project (Boulder)

14th Street

Tennyson St.

S. Broadway
Reconstruction/ Wesley to Yale

Airport Projects
  - Grand Junction Regional
  - Riverton Regional
  - Gunnison-Crested Butte

30th Street Transportation Improvements Project

Conduit 74

S. Broadway
Reconstruction/ Arizona to Iowa

WYDOT - Gillette/Douglas
HWY 59

Ferril Lake at City Park

University Blvd./E. Asbury Ave. Reconstruction

Larimer Square

Hanging Lake Tunnel

Elmer's TwoMile Greenway Project

Denver Water Conduit
Project #25

Winslow Road

GCC Dacotah Cement Terminal

28th & Pearl Improvement Project

Broadway Street & Bridge Reconstruction

Foothills Parkway
& Arapahoe

Glenwood Canyon

Grand Avenue Paving

Roundabouts

Santa Fe Dr. & Belleview

Utilities

 

The Denver Water Conduit #25 project was located on 9th and Hoyt Street, just east of 9th and Kipling in Denver. An old 48” valve and access vault located 20 feet below the street were removed and a new 60” valve was installed. Fifty feet of the old 60” concrete pipe was also replaced to accommodate two new access manholes, a drain manhole, and a new manhole for the new butterfly valve. The new concrete steel pipe, interior and exterior lined, was welded into place.

Concrete Works only had ten days to complete this entire project. While Lakewood High School was on spring break, 9th Avenue (the high school’s main access road) was completely closed for the work. Crews worked from 7:00 a.m. to 9:00 p.m. daily to complete the project and reopen the road before school was back in session following their break.

 
   