Broadway Transportation Improvements Project (Boulder)
14th Street
Tennyson St.
S. Broadway
Reconstruction/ Wesley to Yale
Airport Projects
- Grand Junction Regional
- Riverton Regional
- Gunnison-Crested Butte
30th Street Transportation Improvements Project
Conduit 74
S. Broadway
Reconstruction/ Arizona to Iowa
WYDOT - Gillette/Douglas
HWY 59
Ferril Lake at City Park
University Blvd./E. Asbury Ave. Reconstruction
Larimer Square
Hanging Lake Tunnel
Elmer's TwoMile Greenway Project
Denver Water Conduit
Project #25
Winslow Road
GCC Dacotah Cement Terminal
28th & Pearl Improvement Project
Broadway Street & Bridge Reconstruction
Foothills Parkway
& Arapahoe
Glenwood Canyon
Grand Avenue Paving
Roundabouts
Santa Fe Dr. & Belleview
Utilities
|


The second phase of the S. Broadway Reconstruction Project will begin in early April. This phase will run from Wesley Avenue to Yale Avenue. The project will include the reconstruction of the roadway in new concrete pavement, major drainage and utility upgrades, new signalization, construction of a new raised landscape median and streetscape improvements. Streetscape improvements will include a landscaped median featuring trees and native plantings, sidewalk planters, benches, and decorative street lights.
Public Information:
Information for this project will be available several different ways:
Project information line: 303-419-0884
This line will include a recorded weekly update and the opportunity for the caller to leave a message. The line will be checked throughout the day/7 days a week.
Project email: publicinfo@concreteworksofcolorado.com
Sign up to receive S. Broadway emails which will include weekly project updates and traffic impacts. You may also contact Concrete Works via this email with project questions/concerns. To sign up, send an email to this address.
Abbreviated updates are available on twitter at:
http://twitter.com/ConcreteWorksCO
Sign up for this free service and become a follower of Concrete Works of Colorado/ S. Broadway Reconstruction project.

Streetscape, Plan view of Corridor

View Streetscape, Plan view of Corridor (pdf)








|
|

February 16, 2012:
TWork is moving along well on the west side of S. Broadway. Crews started removals at Wesley last week and they are already up to Harvard. On Monday of next week the removals at Yale will begin. We are still a couple of weeks out on the placement of the new sidewalks along the west side. That work will begin after removals are complete and after the light pole bases are installed.
The final inlet on the project, located at Yale, will be finished up next Tuesday.
Please remember that all work is weather dependent. Concrete Works of Colorado appreciates your patience during this construction. |
|