This FAA project included three separate schedules of work lasting over two working seasons. The highlighted work on the apron and air infield improvement project is 61,500 SY of 4″ lean concrete and 16.5 “full strength concrete removal and replacement.
Airports
Colorado Springs Airport Taxiway M&F Reconstruction
This City of Colorado Springs project, included 30,000 SY of full depth concrete removal and replacement at a 16” depth. The extreme demands of the schedule to complete this work during the winter season in 5 months with 2 phases, 4 milestones, and $10,000 dollar per day liquidated damages made it an intimidating project. However, […]
Grand Junction CO Regional Airport (Walker Field)
This Grand Junction Regional Airport Authority project at Walker Field Airport included the reconstruction of the general aviation apron in four separate phases. The project consisted of the removal of the existing deteriorated 20,000sy of asphalt and 46,000sy of concrete apron and repaving with concrete. In addition, the project included 1,500lf of trench drain with […]